The board conditionally approved a roughly $3.6 million Hornor Basin construction award to Cal Valley Construction, subject to federal environmental clearance. Friant-Kern Canal drawdown is expected around October 23, ahead of a planned November–January shutdown. North Kings GSA allocation figures remain in development; none were adopted. The board approved the Eastside Creeks agreement, documenting existing creek-water priorities and setting measurement cost shares.
The board authorized staff to seek bids for about $583,000 in equipment replacements (dozer, water truck tank, five pickups, brush cutter). Staff reviewed canal segments offline for construction and stormwater-routing constraints, with some work expected to clear by October. North Kings GSA discussed certified letters for suspected unregistered ag wells and a progressive enforcement process that can escalate to liens.
Board approved awarding the $2.8M Big Dry Creek–Friant-Kern Canal turnout project to Nicholas General Engineering Contractors, funded largely by a $2.5M Fresno County ARPA grant (FID covers balance). Board also approved Vernon Drain structure replacement (~$330K). SGMA allocation work continues with initial agency figures nearing completion; well-registration enforcement policy expected Aug/Sept. Biola ribbon cutting celebration July 29.
Water deliveries may end mid-August or sooner, with August availability unknown until the July meeting. Staff discussed a new Tier 2 Class 2 offering of at least 2,745 acre-feet at about $165 per AF (vs. ~$25/AF Tier 1) and said FID may buy it to build a buffer if others decline. Southern Sierra snowpack is ~15% of normal; heat may raise demand.
Water season is underway with projections pointing to a late-July shutoff (August extension unlikely) as May 1 snowpack is ~22% of the April 1 average. The board approved a 5-year, 2,100 AF/yr water sale to Hills Valley at $850/AF (~$1.4M/yr). Staff said waiting until Apr. 1 could have triggered ~12,000 AF of FID spill.